Aramco’s Bold Gas Growth to 2030: What the Master Gas System Expansion Means for Saudi Arabia
/ Insights / Articles / Aramco’s Bold Gas Growth to 2030: What the Master Gas System Expansion Means for Saudi Arabia

Aramco’s Bold Gas Growth to 2030: What the Master Gas System Expansion Means for Saudi Arabia

Published on: Jul 13, 2026 | Author: Marketing & Communications

Aramco’s gas strategy to 2030 is anchored to a stated goal: increase sales gas production capacity by about 80% by 2030 compared with 2021 levels. One account ties the 2021 baseline to 9.2 Bscfd. Aramco has framed the build-out as a way to meet growing domestic demand, support Saudi objectives to diversify the energy mix, displace liquid fuels in domestic power generation, and enhance energy security. The company also links this momentum to financial performance, reporting net income of 392.5 billion SAR for the 2025 fiscal year and operating cash flow of 510.8 billion SAR.

The central upstream asset is Jafurah, a liquids-rich unconventional gas development described as the largest of its kind in the Middle East. It spans about 17,000 sq km and is estimated to contain 229 Tscf of raw gas and 75 Bbbl of condensate and liquids. Aramco confirmed first shale gas production from Jafurah began in December 2025. Phase-one facilities were described as producing 450 MMcfd, with output expected to ramp to roughly 2 Bscfd of sales gas by 2030 as additional phases come online. By 2030, Aramco also targets 420 MMscfd of ethane and about 630,000 bpd of high-value liquids from Jafurah.

Master Gas System Expansion: Transmission and Timing to 2028

Midstream capacity is a key part of the story, and it is where Saudi Arabia’s Master Gas System expansion becomes material. Aramco said the Master Gas System expansion project is progressing according to schedule to meet growing domestic demand while also supplying significant volumes of high-value associated liquids. In project detail, Master Gas System Phase 3 is slated for completion by 2028 and is expected to add 3.15 Bscfd of transmission capacity. Aramco also highlighted that major projects are on track, and it listed further gas additions such as Jafurah Phase 2 at 1,350 MMscfd and a Fadhili gas plant expansion at 1,150 MMscfd, both targeting 2027 completion.

Processing is another bottleneck Aramco is addressing. The Tanajib Gas Plant commenced operations in December 2025 and is expected to reach raw gas processing capacity of 2.6 Bscfd in 2026. The facility processes associated gas from the offshore Marjan and Zuluf fields and coincided with the start-up of the Marjan crude oil increment project. Taken together with Jafurah, Aramco says these developments strengthen its integrated gas portfolio and expand processing capacity at scale, positioning the company to respond to changing market conditions while targeting rising domestic demand.

Read also Tanajib Gas Plant Startup: A Pivotal Step for Saudi Arabia’s Gas Processing Scale

Aramco repeatedly points to domestic power generation as a major sink for additional gas, with one Reuters-based account stating Saudi Arabia uses more than 1 million bpd of crude and fuel oil for domestic power generation, and Aramco aims to replace 500,000 bpd of that by 2030 with gas. That same report noted that at prices around $70 a barrel, 500,000 bpd of crude would generate nearly $12.8 billion in revenue a year, illustrating why displacement could matter financially. Separately, Aramco estimates incremental gas volumes could generate between $12 billion and $15 billion in additional operating cash flow by 2030, subject to market conditions, while it targets roughly 6 MMboed of total gas and associated liquids production under the plan.

What is Aramco targeting for sales gas capacity by 2030 versus 2021?

Aramco says it plans to increase sales gas production capacity by about 80% by 2030 compared with 2021 levels. One report links the 2021 baseline to 9.2 Bscfd.

What are the 2030 output targets from the Jafurah field?

By 2030, Jafurah is expected to deliver up to 2 Bscfd of sales gas, 420 MMscfd of ethane, and about 630,000 bpd of high-value liquids. Aramco confirmed first shale gas production began in December 2025.

How does Saudi Arabia’s Master Gas System expansion change transmission capacity?

Master Gas System Phase 3 is slated for completion by 2028 and is expected to add 3.15 Bscfd of transmission capacity. Aramco says the broader Master Gas System expansion is progressing according to schedule.

What role does the Tanajib Gas Plant play in the gas expansion plan?

Tanajib commenced operations in December 2025 and is expected to reach raw gas processing capacity of 2.6 Bscfd in 2026. It processes associated gas from the offshore Marjan and Zuluf fields.

What cash flow upside does Aramco associate with incremental gas volumes by 2030?

Aramco estimates incremental gas volumes could generate $12 billion to $15 billion in additional operating cash flow by 2030, subject to market conditions. A separate Reuters-based comparison notes nearly $12.8 billion in annual revenue at around $70 a barrel for 500,000 bpd of crude.

Ready to Advance Your Energy Strategy in Saudi Arabia?

We help energy companies, investors, and technology providers turn market momentum into clear strategies, stronger execution, and sustainable growth.

Contact Us Today
Download Whitepaper

/ Contact Us

Let’s discuss how we can support your energy strategy in Saudi Arabia.

 

  • No results found