The saudi arabia nuclear energy program is moving from planning into formal market steps. Saudi Arabia has plans to establish a civil nuclear power industry. Today, virtually all of the country’s electricity is generated by burning fossil fuels. This makes the nuclear plan a major shift in how the country could power future growth.
Saudi Arabia’s 2023 electricity picture shows why leaders keep talking about diversification. Total generation in 2023 was 441 TWh. The generation mix was natural gas at 257 TWh (58%), oil at 182 TWh (41%), and wind at 1.6 TWh. This baseline matters because any new nuclear capacity would enter a system still dominated by oil and gas.

On the nuclear track, Saudi Arabia approved a National Project for Atomic Energy in July 2017. It included plans to build large and small nuclear reactors for electricity production and water desalination. In the same period, the government started approaching international companies for reactor construction and later extended its formal bidding process several times.
Bidders And The Khor Duweihin Reactor Plan
In May 2022, Saudi officials invited technical bids for two planned 1.4 GWe reactors at Khor Duweihin. The site is described as a coastal area between the kingdom’s borders with Qatar and the United Arab Emirates. As of July 2024, China National Nuclear Corporation, EDF of France, the Korea Electric Power Corporation (KEPCO), and Rosatom of Russia reportedly were approved bidders. Saudi Arabia also received bids for project management and consultancy linked to the proposed construction.
Institution building has also been part of the timeline. IAEA officials completed a nuclear infrastructure review in 2018 and issued a final report in January 2019. Saudi Arabia established a Nuclear and Radiological Regulatory Commission in March 2018. In March 2022, it created the Saudi Nuclear Energy Holding Company (SNEHC) to develop and operate planned nuclear facilities.
Looking to 2030, the clearest facts in the sources are about energy mix ambitions and market design, not an operating reactor date. One analysis says Saudi Arabia aims for a sustainable energy mix, with solar and nuclear power potentially accounting for more than half of its power supply by 2040. Separately, an energy minister statement in January 2021 said the country aimed to produce 50% of its electricity from renewables by 2030, with the remaining 50% supplied by natural gas. Against that backdrop, the nuclear program’s “2030 outlook” is best read as a race to finish governance, select a vendor, and execute the Khor Duweihin build path that began with the 2022 bid process.
Who are the approved bidders for the saudi arabia nuclear energy program?
Where are the planned large reactors supposed to be built?
What does Saudi Arabia’s electricity mix look like today?
What key governance steps have been reported for the nuclear program?